Labour Contract or Turnkey: Which One Suits Your Home?
Almost every family that sits down with us in Irinjalakuda asks the same question within the first ten minutes. "Should we give it on labour contract and buy the materials ourselves, or hand over everything?"
It's a fair thing to ask. A relative has probably told you labour contract is cheaper. Someone else has a story about a turnkey builder who cut corners on the tiles. Both stories can be true. The type of contract doesn't decide on its own how your house turns out, but it does decide who carries the risk, who spends the time, and who you call when something goes wrong two monsoons later.
Below we've laid out how each option really works in Kerala, where each one tends to fail, and how to choose based on your own situation rather than on what worked for the family next door.
The short version
| Labour contract | Turnkey contract | |
|---|---|---|
| Who buys materials | You | The builder |
| Your time on site | Several visits a week, sometimes daily | Stage inspections and meetings |
| Price certainty | Low, because prices move and wastage adds up | High, if the specification list is detailed |
| Who answers for defects | Split between contractor and suppliers | One company |
| Suits | Owners who live nearby and know construction | NRIs, working couples, first time builders |
How a labour contract works
Under a labour contract, the contractor brings the masons, helpers, bar benders and shuttering carpenters, and you pay them at a rate per square foot or per stage. Everything else is your job. Cement, steel, M sand and P sand, laterite or concrete blocks, aggregate, water and power for the site, and usually the plumbing and electrical materials as well.
It looks cheaper on paper because the builder's margin on materials disappears. In practice, how much you save depends almost entirely on how well you buy and how often you can be on site.
The things owners tend to underestimate:
- Wastage. Nobody is more careful with cement than the person who paid for it. When the contractor isn't paying for materials, there's not much reason for anyone on site to be careful with them.
- Timing. If the steel arrives three days late, the crew sits idle and you still pay them. Someone has to be ordering ahead, every week, for months.
- Technical choices. You'll be asked which cement to use for the slab, what grade of steel, which waterproofing compound. If you don't know, you'll guess, or you'll ask the contractor, who may well have a dealer he prefers.
- Who owns the problem. If the terrace leaks, the contractor can blame the waterproofing product you bought. The dealer will blame the workmanship. Either way, you pay for the repair.
None of this means labour contracts are a bad idea. We've seen them done very well by retired engineers, and by families with someone experienced in the trade who can be on site most days. It just suits a particular kind of owner.
How a turnkey contract works
In a turnkey (or full) contract, the builder supplies both labour and materials and hands over a finished house for an agreed price, usually quoted per square foot or as a lump sum for your plan. A proper turnkey contract also includes supervision and scheduling, so the plumber and electrician arrive at the right stage and not after the plastering is finished.
The main advantage is that one company is responsible. If a wall cracks or a bathroom leaks into the room below, there is one number to call.
The risk also sits in one place, and that place is the specification list. Two builders can quote almost the same rate per square foot and deliver very different houses. The difference hides in lines like "vitrified tiles" (what size, which brand, what price per square foot?) or "branded sanitary fittings" (which brand, and which range?).
The specification sheet is where most turnkey deals go wrong
Before comparing any two quotes, ask each builder for the full specification sheet. At the very least it should name:
- Cement brand and grade, and steel brand and grade (for example Fe 500 or Fe 500D)
- Concrete mix for the footings, columns and slabs
- Wall material and block size
- Flooring type and size, with an allowance per square foot for the tile itself
- Main door wood, other door material, and window frame type
- Sanitaryware and bathroom fittings, with brand and model range
- Wire and switch brands, and the number of electrical points in each room
- Plumbing pipe brand and class
- Paint brand and product for inside and outside, with the number of coats
- Waterproofing method for the terrace, bathrooms and sunshades
Then look just as carefully at what has been left out. These are the items that most often come back later as "extra work":
- Compound wall and gate
- Well, borewell, sump or overhead tank
- Septic tank and soak pit
- KSEB and water connection deposits
- Permit and plan approval fees
- Site clearing, filling, or deeper foundations if the soil turns out to be poor
- Interiors, modular kitchen and wardrobes
A quote that looks noticeably cheaper per square foot often stops looking cheap once these are added back in. If a builder is reluctant to put brands and exclusions in writing, treat that as your answer.
Link payments to stages, not dates
Whichever contract you choose, money should follow work that has actually been done and checked. A typical stage schedule looks something like this:
- Agreement and setting out on site
- Foundation and plinth, including the plinth belt
- Ground floor lintel
- Ground floor roof slab
- First floor slab, for two storey homes
- Plastering
- Flooring and tiling
- Painting, fittings and handover
Hold back a small final amount until a fixed period after handover, so that the little snags that always show up in the first few months get fixed without a chase.
What happens when prices go up?
Cement and steel prices move through the year. On a labour contract, every increase comes straight out of your pocket. On a turnkey contract, read the escalation clause before you sign. Some builders hold the price for the whole project. Others hold it for a fixed period, or reserve the right to revise if steel moves past a certain percentage. Neither approach is wrong, but you should know which one you agreed to.
So which one should you choose?
A labour contract usually makes sense if:
- You, or someone you trust completely, live close to the site
- That person understands materials and site work
- You can make decisions quickly and pay suppliers on time
- You're comfortable sorting out disputes yourself
A turnkey contract usually makes sense if:
- You work in the Gulf or another city, as so many Thrissur families do
- Both of you have full time jobs
- This is your first house
- You want the budget fixed before the first footing is dug
Some families take a middle path. They go turnkey for the structure up to plastering, then choose their own tiles, sanitaryware and interiors. That can work well, as long as the contract is clear about who is responsible where the two parts meet. A tile that sounds hollow because the bed underneath wasn't prepared properly is a classic argument waiting to happen.
Questions to ask any builder before you sign
- Can I have the full specification list in writing, with brands?
- What exactly is not included in this quote?
- Who will supervise the site day to day, and how often will an engineer visit?
- How are payments linked to stages?
- What happens if material prices rise halfway through?
- What guarantee do you give on the structure and waterproofing, and is it in the agreement?
- Can I visit a house you finished at least two years ago?
That last question matters more than any brochure or 3D render. Every house looks perfect on handover day. Two monsoons later, you find out how it was built.
How we work at Design Draft
Most of the homes we build around Thrissur are turnkey projects, because the families we work with want one team responsible from the first drawing to the day they get the keys. Every quote comes with a detailed specification sheet and a stage wise payment plan, so you know what you're paying for at each step.
If you already have quotes from other builders, bring them along. We're happy to go through them with you so you're comparing like with like. You can book a consultation, call us on +91 7736885666, or read our construction cost guide for Thrissur first to get a feel for the numbers.
Frequently Asked Questions
Is a labour contract cheaper than turnkey construction in Kerala?
It can be on paper, because you are not paying the builder a margin on materials. The real saving depends on how well you buy, how much material is wasted, and how much time you can spend on site. For owners who cannot visit often, wastage, delays and repair disputes usually eat into the difference.
What is usually included in a turnkey house construction contract?
A turnkey contract normally covers labour, materials, supervision and handover of a finished house as per an agreed plan and specification. Items such as the compound wall, well, sump, septic tank, utility deposits, permit fees and interiors are often excluded, so always ask for the list of exclusions in writing.
Can I choose my own tiles and fittings in a turnkey contract?
Yes. Many builders give an allowance per square foot for tiles and a set budget for fittings, and you can pick within that or pay the difference for something more expensive. Some families also keep finishes completely out of the contract and buy them separately.
How do I compare two turnkey quotes fairly?
Put the specification sheets side by side and check the brands, grades, tile allowances, number of electrical points and the list of exclusions. Two quotes with the same rate per square foot can describe very different houses.